ION Construction Update
Updated: July 21, 2017

Construction of Stage 1 ION, the Region of Waterloo’s light rail transit (LRT) service is nearing completion. Final paving operations are on-going along the ION route, and are expected to be completed this summer. This work requires short-term, full road closures to allow for application, curing and striping of the new asphalt.

Read on to find out what’s happening, when and where. Remember that the timing of all work is subject to weather conditions and construction constraints.

ION testing: The ION trains and LRT system will soon be tested. Visit this webpage to learn more about ION LRT safety.

Downtown Kitchener


Getting Around

  • Final asphalt paving and striping has been completed on Charles (Victoria to Benton), Duke (Francis to Queen), Frederick (Duke to Benton), King (Victoria to Francis) and Victoria (Charles to King)

  • The following closures are required for the installation of enhanced pedestrian crossings:

    • On or about July 24, at night, (7 p.m. to 7 a.m.) the King/Victoria intersection will close for approximately one night

    • On or about July 25, at night (7 p.m. to 7 a.m.), the Duke/Young intersection will close for approximately one night

    • On or about July 26, at night (7 p.m. to 7 a.m.), the Duke/Frederick intersection will close for approximately one night

    • On or about July 27, at night (7 p.m. to 7 a.m.), the King/Benton intersection will close for approximately one night

  • In late-July, Kitchener Wilmot Hydro work will require the closure of Duke, between Ontario and Queen, until approximately August 25

Construction

  • Installation of signage, equipment and furnishings, including: benches and bike racks at the Kitchener City Hall, Victoria Park, Queen and Frederick ION stops. The light features and security cameras at these stops have been activated

Night work

  • Until approximately late-July, crews are periodically working at night (7 p.m. to 7 a.m.) on Victoria (Charles to Duke), Charles (Victoria to Borden), Frederick (Duke to Charles) and Duke (Francis to Frederick)


More Information

For information on Grand River Transit bus routes, please visit the GRT website:www.grt.ca.


Visit www.rideion.ca for information specific to each ION construction area.If you have any questions related to ION construction, please email us at connect@rideion.ca or call us at1-844-625-1010.

Thank you for your continued interest in ION – Waterloo Region’s new light rail transit service set to begin service in 2018.


Let's Build it!


ION Construction Update

Please note the timing for the upcoming closures on Duke, from Francis to Frederick, and on Frederick, from Duke to Benton, has been revised as follows:

  • Duke, Francis to Ontario, will close nightly (7 p.m. to 7a.m.) on or about July 10 for approximately three nights

    • Intersections impacted: Duke/Water, Duke/College, Duke/Young and Duke/Ontario

  • Duke, Ontario to Frederick, will close at nightly (7 p.m. to 7a.m.) on or about July 11 for approximately three nights

      • Intersections impacted: Duke/Ontario, Duke/Frederick, Duke/Queen

  • Frederick, Duke to Charles, will close nightly (7 p.m. to 7 a.m.) on or about July 11 for approximately three nights

      • Intersections impacted: Frederick/King, and Frederick/Duke

      • In preparation for final asphalt paving King/ Frederick will close on or about July 8 for one day


ION Construction Update
Updated: June 30, 2017

Construction of Stage 1 ION, the Region of Waterloo’s light rail transit (LRT) service is nearing completion. Final paving operations are underway along the ION route, and are expected to be completed by the fall. This work will require short-term, full road closures to allow for application, curing and striping of the asphalt.

Read on to find out what’s happening, when and where. Remember that the timing of all work is subject to weather conditions and construction constraints.

ION Video: Ever wondered how ION trains are operated?Check out this quick video to learn more.

Progress updates: For ION construction progress updates visit thisProject Updatespage.

ION testing: The ION trains and LRT system will soon be tested. Visit this webpage to learn more about ION LRT safety.

New Construction Highlights

Midtown


Getting Around

  • In mid-July, King, from Moore to Victoria (including the King/Moore intersection), will re-open to vehicular traffic

    • Pedestrian/cycling access has been reinstated

    • The area will close temporarily for final asphalt placement and other finishing work later this summer

  • Short-term lane restrictions may be required to complete work on King, Victoria, Francis and Charles

Construction

  • Building of the Grand River Hospital and Central Station-Innovation District ION stops

  • LRT track installation between on King, between Wellington and Victoria

  • Final surface work at the GRT bus shelters on King (Union to Victoria) will be on-going until mid-July

Night work

  • Until approximately late-July, crews are periodically working at night (7 p.m. to 7 a.m.) on King, from Union to Victoria


Downtown Kitchener


Getting Around

  • Crews continue to complete final asphalt paving in Downtown Kitchener. The following road closures are required as a result:

    • On or about July 3, Charles (Victoria to Water) will close nightly(7 p.m. to 7a.m.) for approximately two nights

      • Intersections impacted: Charles/Water and Charles/Francis

    • On or about July 9, Duke (Francis to Ontario) will close nightly(7 p.m. to 7a.m.) for approximately two nights

      • Intersections impacted: Duke/Water, Duke/College, Duke/Young and Duke/Ontario

    • On or about July 10, Duke (Ontario to Frederick) will close nightly(7 p.m. to 7a.m.) for approximately two nights

      • Intersections impacted: Duke/Queen and Duke/Frederick

      • In preparation for final asphalt paving, the following intersections will need to close for one day:

        • Duke/Water - on or about July 5

        • Duke/Ontario - on or about July 5

        • Duke/ Queen - on or about July 6

        • Duke/Young - on or about July 6

        • Duke/Frederick - on or about July 7

    • On or about July 10, Frederick (Duke to Benton) will close nightly(7 p.m. to 7a.m.)for approximately two days

      • Intersections impacted: Frederick/King and Frederick/Duke

      • In preparation for final asphalt paving, King/ Frederick will close on or about July 8 for one day

  • Duke (between Queen and the Duke Street parking garage) is closed until approximately mid- July. Access to the Ontario Street Parking Garage is maintained

  • On or about July 4, King at Francis (south side) will close for approximately three days

    • Through traffic on Francis will be maintained during this work

  • On or about July 10, King at Benton (north side) will close for approximately two days

    • Through traffic on Benton will be maintained during this work

Construction

  • Final asphalt paving on Charles (Queen to Benton),Charles (Victoria to Water), andDuke (Francis to Frederick) is on-going

  • Installation of signage, equipment and furnishings, including: benches, trash receptacles and bike racks at the Kitchener City Hall, Victoria Park, Queen and Frederick ION stops. The light features and security cameras at these stops have been activated

  • Final surface work at the GRT bus shelters on Frederick/Benton, from King to Charles, will be on-going until mid-July

Night work

  • Until approximately late-July, crews are periodically working at night (7 p.m. to 7 a.m.) on Victoria (Charles to Duke), Charles (Victoria to Borden), Frederick (Duke to Charles) and Duke (Francis to Frederick)


More Information

For information on Grand River Transit bus routes, please visit the GRT website:www.grt.ca.
Visitwww.rideion.cafor information specific to each ION construction area.If you have any questions related to ION construction, please email us atconnect@rideion.caor call us at1-844-625-1010.

Thank you for your continued interest in ION – Waterloo Region’s new light rail transit service set to begin service in 2018.



Road and Lane Closure Notifications

Effective: Wednesday, June 21, 2017 2:10 p.m.

https://rowpages.regionofwaterloo.ca/RoadClosures/RoadClosure 



Road and Lane Closure Notifications

Effective: Monday, June 19, 2017 4:10 p.m.

https://rowpages.regionofwaterloo.ca/RoadClosures/RoadClosure 


ION Construction Update
Updated: June 16, 2017

Construction of Stage 1 ION, the Region of Waterloo’s light rail transit (LRT) service is nearing completion. Final paving operations are getting underway along the ION route, and are expected to be completed by the fall. This work will require short-term, full road closures to allow for application, curing and striping of the asphalt.

Read on to find out what’s happening, when and where. Remember that the timing of all work is subject to weather conditions and construction constraints.

ION Video: Ever wondered how ION trains are operated? Check out this quick video to learn more.

Progress updates: For ION construction progress updates visit thisProject Updatespage.

ION testing: The ION trains and LRT system will soon be tested. Visit this webpage to learn more about ION LRT safety.

Downtown Kitchener


Getting Around

  • Starting as early as June 18, crews will begin to complete final asphalt paving in Downtown Kitchener. The following closures are required for this work:

    • Victoria, from Waterloo to Charles, will close nightly on or about June 18 at (7 p.m. to 7a.m.) for approximately two nights

      • Intersections impacted: Victoria/Charles and Victoria/King

    • King, from Victoria to Francis, will close nightly on or about June 19 (7 p.m. to 7a.m.) for approximately two nights

      • Intersection impacted: King/Francis

    • Francis, from King to Duke, will close nightly on or about June19 (7 p.m. to 7a.m.) for approximately two nights

      • Intersection impacted: Francis/Duke

  • Charles, Victoria to Gaukel, will close nightly on or about June 22 (7 p.m. to 7a.m.) for approximately two nights

    • Intersections impacted: Charles/ Francis; Charles/Water; Charles/ Gaukel,

    • In preparation for this paving the following intersections will need to close for one day:

      • Charles/Francis will close on or about June 20

      • Charles/Gaukel will close on or about June 20

      • Charles/Water will close on or about June 21

  • Charles, Gaukel to Benton, will close nightly on or about June 26 (7 p.m. to 7a.m.) for approximately two nights

    • Intersections impacted: Charles/Ontario; Charles/Queen

    • In preparation for this paving the following intersections will need to close for one day:

      • Charles/Queen will close on or about June 20

      • Charles/Ontario will close on or about June 21

      • Charles/Benton will close on or about June 22

  • Duke, between Queen and the Duke Street parking garage, is closed until approximately June 23 for Kitchener-Wilmot Hydro work.

  • Short-term lane restrictions may be required to complete work on Duke and Frederick

Construction

  • Final asphalt paving along Victoria (Waterloo to Charles), King (Victoria to Francis), and Francis (King to Duke)

  • Installation of LRT track on Frederick, from Duke to King

  • Installation of signage, equipment and furnishings including benches, trash receptacles and bike racks at the Kitchener City Hall, Victoria Park, Queen and Frederick ION stops. The light features and security cameras have been activated at these ION stops

  • Work to install the GRT bus shelters on Frederick/Benton from King to Charles, will continue through late-June

  • Work to prepare the embedded track for sealing application

Night work

  • Until approximately late-July, crews are periodically working at night (7 p.m. to 7 a.m.) on Victoria (Charles to Duke), Charles (Victoria to Borden), Frederick (Duke to Charles) and Duke (Francis to Frederick)


More Information

For information on Grand River Transit bus routes, please visit the GRT website:www.grt.ca.
Visitwww.rideion.cafor information specific to each ION construction area.If you have any questions related to ION construction, please email us atconnect@rideion.caor call us at1-844-625-1010.

Thank you for your continued interest in ION – Waterloo Region’s new light rail transit service set to begin service in 2018.



ION CONSTRUCTION UPDATE                           
Downtown Kitchener 
 
GrandLinq has advised the Region of Waterloo that they will complete final asphalt paving in areas of Downtown Kitchener.
 
The work will see the final layer of asphalt placed from June 18 - 27, in a series of separate nightly road closures. A breakdown of the areas impacted each night is included below.
 
During this work, GrandLinq crews plan to place asphalt and stripe the road at night. The road will re-open during the day.
 
The work is subject to construction constraints and weather conditions. Final asphalt cannot be placed in wet or humid weather. If this occurs, the work will be re-scheduled and will be communicated to all stakeholders as well as posted on the ION construction website.

Victoria (Waterloo to Charles)
  • June 18-19, full road closures at night beginning at 7 p.m.

  • The road will be re-opened during the day

  • Intersections impacted:

  • Victoria/King; Victoria/Charles

King (Victoria to Francis) and Francis (King to Duke)
  • June 19-20, full road closures at night beginning at 7 p.m.

  • The road will be re-opened during the day

  • Intersections impacted:

  • King/Francis; Francis/Duke

Charles (Victoria to Gaukel)
  • June 22-23, full road closures at night beginning at 7 p.m.

  • The road will be re-opened during the day

  • Intersections impacted:

  • Charles/Francis; Charles/Water; Charles/Gaukel

  • In preparation for this paving, the following intersections will need to close for one day:

  • Charles/Francis; Charles/Gaukel intersections will close on or about June 20

  • Charles/Water intersection will close on or about June 21

Charles (Gaukel to Benton)
  • June 26-27, full road closures at night beginning at 7 p.m.

  • The road will be re-opened during the day

  • Intersections impacted:

  • Charles/Ontario; Charles/Queen; Charles/Benton

  • In preparation for this paving, the following intersections will need to close for one day:

  • Charles/Queen intersection will close on or about June 20

  • Charles/Ontario intersection will close on or about June 21

  • Charles/ Benton intersection will close on or about June 22


Road and Lane Closure Notifications

Effective: Monday, June 12, 2017 1:05 p.m.

https://rowpages.regionofwaterloo.ca/RoadClosures/RoadClosure 


Road and Lane Closure Notifications

Effective: Monday, June 5, 2017 9:10 a.m.

https://rowpages.regionofwaterloo.ca/RoadClosures/RoadClosure 


Paving Schedule for Halls Lane

Below is an updated paving plan for Halls Lane:

Benton Street to Eby Street – Ongoing Monday May 29th. Paving to start at 7:00am at concrete walkway and head towards Eby St. this section is to be completed by around 12 Noon. At 12 Noon start paving from concrete walkway to Benton St. this section to be completed by 3;00pm.. We ask that all vehicles be removed from Halls Lane for this paving operation. Vehicles left in the way of the paving operation, will be towed. Paving by the Crown Plaza Hotel is planned between the Hours of 11am – 3pm.

Benton Street to Queen Street– Monday May 29th. Paving to start around 3:00pm at the Benton St end and continue to as far as they can get by the 6 - 7:00pm.. We ask that all vehicles be removed from Halls Lane for this paving operation. Vehicles left in the way of the paving operation, will be towed.

Ontario Street to Queen - Scheduled to take place on Tuesday May 30th starting at 6:00am. Paving will start at Ontario St. at 6:00am and pave past the Parking Garage of the NetSuite building by 9:00am. The Parking Garage will be closed off to traffic until we get the new asphalt back rolled and cooled down. Once the asphalt is cooled down the Parking Garage will be opened to traffic by around 9:00am. After 9;00am the Paving Operation will continue to finish the Block between Ontario and Queen.. Vehicles left in the way of the paving operation, will be towed. Paving by the Walper Hotel is planned between the Hours of 11am – 3pm.


Road and Lane Closure Notifications

Effective: Thursday, May 25, 2017 - 4:25 p.m.

https://rowpages.regionofwaterloo.ca/RoadClosures/RoadClosure 